A piece count does not determine total metres unless the length of each piece is known.
Technical considerations
A piece count does not determine total metres unless the length of each piece is known. Multiply count by length on every line, then apply the approximate kg/m value for that section. Do not combine different wall thicknesses as though they were one product. For short parts, include kerf and end-trim allowances in purchasing. When converting a weight budget into pieces, confirm whole-piece and minimum-order rules separately. Rounded corners can also create a difference between a simplified area calculation and the manufacturer's published section data.
Track different lengths within the same section
Twenty 1.2 m pieces and ten 2 m pieces of the same section require 44 m net material. The number of stock lengths depends on nesting. Purchased piece count is not interchangeable with net metres. Show cutting allowance separately in a theoretical mass budget so changes to the part schedule can be updated without concealing the loss assumptions.
Are net metres the purchased metres?
Not always. Kerf and stock-length nesting may increase the purchase quantity.